1. Introduction

Dúnta13 Nol, 2019, 9:00am - 3 Fea, 2020, 5:00pm

As part of Coonagh Knockalisheen Distributor Road a Part 8 is being lodged to dispose of uncontaminated inert soil and stone at Ballygrennan, Limerick. The proposed development comprises:-

•             The reuse of uncontaminated inert soil and stone material excavated as part of the Coonagh Knockalisheen Distributor Road project as landscape fill on lands bounding the scheme. The proposed finished ground levels of the proposed development will help to integrate the road embankment into the surrounding landscape at Ballygrennan.

•             The overall landscape fill volume comprising of the excavated soil and stone is 26,000m3 within the original Compulsory Purchase Order boundary and 39,000m3 on lands outside the Compulsory Purchase Order. This is equivalent to approximately 47,000 tonnes within the original Compulsory Purchase Order boundary and approximately 72,000 tonnes outside the Compulsory Purchase Order.

Irish Water’s observations regarding Part VIII planning application for Landscape Fill Area Ballygrennan
Dear Sir/Madam, In response to referral for a Part 8 development on lands in the townland of Ballygrennan, Limerick received on 17/12/2019 from Limerick City...
Notice of Proposed Development
Irish Rail have no observations or submission to make.
Planning Ref: PART 8 Landfill
Re: Notification to the Minister for Culture, Heritage and the Gaeltacht under Article 28 (Part 4) or Article 82 (Part 8) of the Planning and Development Regulations, 2001, as amended.
Part 8 Proposal - Landscape Fill Area at Ballygrennan, Co. Limerick
TII has no specific observations to make in relation to the development.